Contents

                        Executive summary                                                             

1                      Introduction                                                                          

1.1                   Purpose of the Report                                                     

2                      Environmental Status                                                      

2.1                   Project Area                                                                         

2.2                   Environmental Sensitive Receivers                            

2.3                   Major Construction Activities                                     

2.4                   Monitoring Schedule of The Reporting Month    

2.5                   Status of Environmental Approval Documents

2.6                   Community Liaison Group Meeting                               

2.7                   Summary of Non-Compliance With The Environmental Quality Performance Limits                                                                                           

2.8                   Summary of Environmental Complaints                  

2.9                   Summary of Environmental Summons                      

3                      Environmental Issues and Actions                             

3.1                   Previous Environmental Deficiencies and Follow-up Actions       

3.2                   Implementation Status on Environmental Protection Requirements

4                      Environmental Monitoring                                             

4.1                   Air and Noise                                                                           

4.2                   Water Quality                                                                        

4.3                   POPs Monitoring                                                                   

4.4                   Waste Management                                                             

4.5                   Cultural Heritage                                                              

4.6                   Landscape and Visual                                                        

4.7                   Land Contamination, Hazard to Life and Fuel Spill Risk 

4.8                   Ecology                                                                                    

4.9                   EM&A Manual                                                                          

4.10                 Baseline Water Quality Monitoring                           

5                      Future Key Issues                                                                 

5.1                   Key Issues for the Next One Month                            

5.2                   Impact Prediction for the Next One Month            

5.3                   Works and Monitoring Schedule for the Next One Month    

 

LIST OF TABLES

Table 2.1        Summary of Works Undertaken During the Reporting Period

Table 2.2        Cumulative Quantity of Excavated Marine Sediments up to 31 October 2008

Table 2.3        Summary of Environmental Licensing, Notification and Permit Status

 

LIST OF ANNEXES

 

Annex A     Project Location

Annex B     Water Quality Monitoring Stations, Water Quality and Ecological Sensitive Receivers

Annex C     Monitoring Schedule for the Reporting Period and Next Month

Annex D     Cumulative Complaints Statistics

Annex E     Implementation Programme of Mitigation Measures

Annex F     QA/QC Results of Laboratory Testing for Suspended Solids

Annex G     Impact Water Quality Monitoring Results

Annex H     Monitoring Results and QA/QC Reports of Laboratory Testing for POPs

Annex I      Dolphin Sighting Records

 


EXECUTIVE SUMMARY

The construction works for the Permanent Aviation Fuel Facility resumed on 9 July 2007.  This twenty-fourth monthly Environmental Monitoring and Audit (EM&A) report presents the EM&A work carried out during the period from 1 October to 31 October 2008 in accordance with the EM&A Manual.

Breaches of all Action and Limit Levels

No exceedance of depth-averaged Turbidity, depth-averaged Suspended Solids (SS) and depth-averaged Dissolved Oxygen (DO) was recorded during the monitoring month.   

Complaint Log

No environmental complaints were received during the reporting period.

Notifications of any Summons and Successful Prosecutions

No environmental summon or prosecutions were received in this reporting period.

Reporting Changes

There were no reporting changes in the reporting period. 

Future Key Issues

·         Dust release and suppression;

·         Operation of dredging activities; and

·         Water quality monitoring and dolphin monitoring during the dredging activities.

 

 


1                                            Introduction

Leighton Contractors (Asia) Limited (LCAL) has appointed ERM-Hong Kong, Limited (ERM) as the Environmental Team (ET) to implement the Environmental Monitoring and Audit (EM&A) programme for the Permanent Aviation Fuel Facility (the Project) during construction works. 

The construction works for PAFF commenced in November 2005 based upon the previous EIA (EIAO Register Number AEIAR-062-2002) conducted and the Environmental Permit EP-139/2002 granted on the 28th August 2002.  Due to minor changes to the detailed layout of the site and the site boundary, application for Variation to the Environmental Permit (VEP) (VEP-133/2004) was submitted to the Director of Environmental Protection (DEP) for approval.  The variation to the EP (EP-139/2002/A) was granted by the EPD in February 2004.

The decision by the EPD to grant the above Environmental Permit was, however, subject to a Judicial Review.  The Judicial Review sided in the favour of the DEP, as did the subsequent Judgement from the Court of Appeal from the High Court for Judicial Review in March 2005.  However, the DEP’s decision to grant the EP was quashed by the Judgement of the Court of Final Appeal of July 2006.

The construction works were stopped following the Judgement of the Court of Final Appeal of July 2006.  As such, in order to continue with the construction of the project, the project went through the statutory procedures under the EIAO again with a new design in order to obtain an environmental permit.  The revised EIA was submitted in 2007 and the environmental permit (EP-262/2007) was granted in May 2007.  EP-262/2007 has been amended to EP-262/2007/A and issued by the EPD on 30 November 2007.  A further Variation to the Environmental Permit has been approved to allow dredging works to continue until March 2008.  As such, EP-262/2007/A has been amended to EP-262/2007/B and issued by the EPD on 27 February 2008.

The construction works and EM&A requirements were resumed on 9th July 2007 following the latest requirements of the EP-262/2007/B and EM&A Manual.  Details regarding the EM&A requirements and changes should refer to the updated EM&A Manual.  For the marine works, all piling activities were completed before the previous suspension of construction works in 2006.

1.1                                      Purpose of the Report

This is the twenty-fourth EM&A Report which summarizes the monitoring results and audit findings for the EM&A programme during the reporting period from 1 October to 31 October 2008.

 

 

2                                            Environmental Status

2.1                                      Project Area

The project area is in Area 38 of Tuen Mun and the pipelines are located in Urmston Road between Tuen Mun Area 38 and Sha Chau.  The site is illustrated in Annex A.

2.2                                      Environmental Sensitive Receivers

No air and noise sensitive receivers were identified close to the project area.  However, water sensitive receivers and ecological sensitive receivers were identified in the EIA study, and are shown in Annex B.

2.3                                      Major Construction Activities

A summary of the major works undertaken in this reporting period is shown in Table 2.1.  Dredging operation was suspended from 1 April to 31 August 2008 and resumed on 1 September 2008.  Table 2.2 presents the cumulative quantity of excavated materials up to 31 October 2008.  Daily and cumulative dredging production rates are illustrated in Figure 2.1.

Table 2.1        Summary of Works Undertaken During the Reporting Period

Area

Works undertaken

Tuen Mun Area 38

Tank Farm, Roof Truss and Bund Wall Construction

Permanent Drainage Construction

Operational & Fire Services Buildings Construction

Jetty Works (Non-piling)

 

Submarine Pipeline Route

Dredging Operations

Table 2.2        Cumulative Quantity of Excavated Marine Sediments up to 31 October 2008

Type of Excavated Materials

Cumulative Bulk Volume (m3)

From 17 December 2007 to 31 March 2008

 

Contaminated Mud

105,974

Uncontaminated Mud

97,815

 

 

From 1 September to 31 October 2008

 

Contaminated Mud

0

Uncontaminated Mud

37,217

2.4                                      Monitoring Schedule of The Reporting Month

Daily water quality monitoring during dredging activities recommenced on 1 September 2008.  The monitoring schedule for October 2008 is presented in Annex C.

2.5                                      Status of Environmental Approval Documents

A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project since July 2007 is presented in Table 2.3. 

Table 2.3        Summary of Environmental Licensing, Notification and Permit Status

Permit/ Licenses/ Notification

Reference

Validity Period

Remarks

Environmental Permit

EP-262/2007/B

Throughout Project

Issued on 27 February 2008 (EP-262/2007/A on 30 November 2007, EP-262/2007 issued on 31 May 2007, EP-139/2002 originally granted on 28 August 2002 and EP-139/2002/A granted on 24 February 2004 were superseded)

 

 

 

 

 

Chemical Waste Producer Registration

 

WPN 5111-421-L2174-25

Throughout Project

Issued on 10 November 2005

Notification of Construction Works under Air Pollution Control (Construction Dust) Regulation

 

H2104/U1D/5542/DG/DH/PL

 

Throughout Project

Notification on 6 July 2007

Construction Noise Permit

GW-RW0676-07

21 December 2007 to 19 June 2008

 

For land-based works including air compressors, breakers, excavators, wheeled loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar benders/cutters, wood saws, grinders, submarine water pump, lorries with crane, dump trucks, rollers, ventilation fans and generators

 

 

GW-RW0677-07

21 December 2007 to 29 February 2008

For marine dredging operation including grab dredger, tug boat, split hopper barge and motor sampan

 

 

GW-RW0678-07

21 December 2007 to 18 June 2008

 

 

For marine jetty works including concrete pump derrick barges, hand-held grinders, generators, air compressors, boring machines, water pumps, tug boat, grout mixers and grout pumps

 

 

GW-RW0094-08

1 March to 31 March 2008

For marine dredging operation including grab dredger, tug boat, split hopper barge and motor sampan

 

 

GW-RW0312-08

04 July 2008 to 22 December 2008

 

 

For marine jetty works including concrete pump derrick barges, hand-held grinders, generators, air compressors, boring machines, water pumps, tug boat, grout mixers and grout pumps

 

 

GW-RW0313-08

04 July 2008 to 19 December 2008

 

For land-based works including air compressors, breakers, excavators, wheeled loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar benders/cutters, wood saws, grinders, submarine water pump, lorries with crane, dump trucks, rollers, ventilation fans and generators

 

 

GW-RW0373-08

1 August 2008 to 20 January 2009

For land-based works including air compressors, breakers, excavators, wheeled loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar benders/cutters, wood saws, grinders, submarine water pump, lorries with crane, dump trucks, rollers, ventilation fans, generators, stirrer, jet chisel, water jet machine and dehumidifier

 

 

GW-RW0368-08

1 September to 30 November 2008

For marine dredging operation including grab dredger, tug boat, split hopper barge and motor sampan

 

Marine Dumping Permit

EP/MD/08-064

13 December 2007 to 29 February 2008

 

For Type 1 – Open Sea Disposal

 

EP/MD/08-065

13 December 2007 to 12 January 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/08-071

13 January 2008 to 12 February 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/08-090

3 March to 31 March 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/08-091

3 March to 31 March 2008

 

For Type 1 – Open Sea Disposal

 

EP/MD/09-018

1 September to 30 September 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/09-032

1 October to 31 October 2008

 

For Type 1d & Type 2 marine disposal

 

 

 

EP/MD/09-017

1 September to 30 November 2008

 

For Type 1 – Open Sea Disposal

Wastewater Discharge License

EP760/421/011399/l

15 March 2006 to 31 March 2011

Issued on 15 March 2006

2.6                                      Community Liaison Group Meeting

According to the EP requirements, a Community Liaison Group (CLG) shall be established within three months after commencement of construction of the Project.  The major duty of the CLG is to advise on and monitor the proper design, construction and operation of the Project.  The CLG comprises representatives from Airport Authority, members of Tuen Mun community and academics. 

The details of the CLG (including Membership and its Terms of Reference) can be found on the Project website (http://www.paffhk.com).

2.7                                      Summary of Non-Compliance With The Environmental Quality Performance Limits

No environmental non-compliance was recorded during the reporting period. 

2.8                                      Summary of Environmental Complaints

No environmental complaints were received during the reporting period.  A summary of environmental complaints since project commencement is presented in Annex D.

2.9                                      Summary of Environmental Summons

No summons was received in this reporting period.  A summary of legal proceeding since project commencement is presented in Annex D.

 

 

3                                            Environmental Issues and Actions

3.1                                      Previous Environmental Deficiencies and Follow-up Actions

As no environmental complaint was received over the last reporting period, no follow-up action was required.

Weekly site inspections were carried out by the ET on 2, 10, 15, 24 and 30 October 2008.  Overall, the site was in good orderly manner and no non-compliances were found.  Environmental deficiencies and follow-up actions/mitigation measures were identified during the inspections, as follows:

Air Quality

·            Water tankers were used regularly to wet the road surface to minimize dust emission.

·            Site entrance was paved and wheel-washing facility was provided to avoid dust deposit on the public road.

·            Main access road within the site (between site office and exit) was paved to avoid dust emission.  Other sections of the major access road in the construction area were paved with stones.

·            On 24 October 2008, open sand piles were observed outside the operation building.  On 30 October 2008, open sand and soil piles were observed near the tank farms and surcharge area.  The Contractor was reminded to cover open piles with impervious sheets in non-working hours.

Noise

·            No noisy activities that generated excessive noise were observed during the audit.

·            All air compressors inspected on site were operated with a valid noise label.

Water Quality

·            Site toilets were provided on site.  A soil soakaway system with holding tanks was installed to treat the sewage from the toilets.  No effluent discharge out of the site was observed during the audits.

·            During the site inspection on 2 October 2008, silt curtains were not properly installed in the dredging area.  The Contactor was recommended to ensure silt curtains were properly installed prior to all dredging activities.

·            During the site inspections on 15 October 2008, sediment plumes were observed in the water at the discharge outlet near the operation building.  The Contractor was recommended to check the efficiency of sedimentation facilities and to review the effluent discharge arrangements in the tank farm area.

·            During the site inspections on 24 October 2008, oil sheen was observed on the edge of the dredging barge deck.  A hose nearby was observed to be leaking, and part of the oil sheen was flushed onto the sea surface.  The Contractor was recommended to arrange clearance of the oil sheen as soon as possible.

·            During the site inspection on 30 October 2008, the oil interceptor and the car washing facility was observed to be filled with sediments.  The Contractor was recommended to clear the sediments in the respective facilities as soon as possible.

Waste Management

·            During the site inspection on 2 and 9 October 2008, chemical wastes were stored on the deck of the barge without spillage preventive measures.  On 15 October 2008, the chemical waste storage area on the dredging barge was observed to be full.  Drums of chemical wastes were placed on the deck of the dredging barge without spillage preventive measures.  The Contractor was recommended to store chemical wastes in bunded areas to avoid potential spillages and arranged collection as soon as the storage area is full.

·            During the site inspection on 15 October 2008, it was observed that wastes were piled up on ground next to the operation building without refuse bin.  The Contractor was recommended to replace refuse bin for temporary storage of general refuse as soon as possible.

·            During the site inspection on 2 and 10 October 2008, oil was observed on the floor behind the workshop.  On 24 October 2008, oil stains were observed on the ground under a pile of unused oil hose outside the operation building.  The Contractor was recommended to clear all oil stains as soon as possible.

·            During the site inspection on 2 October 2008, waste drums in the chemical waste storage were not labelled.  On 15 October 2008, chemical waste drums on the dredging barge were not labelled.  The Contractor was recommended to label the containers with proper stickers with reference to the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes under the Waste Disposal Ordinance (Cap. 354).

·            During the site inspection on 2 and 10 October 2008, machinery inside the workshop was placed on the floor without drip trays.  The Contractor was recommended to provide drip trays for the temporary storage of oily machines in works area.

·            On 2 October 2008, water was observed in the chemical waste storage.  The Contractor was recommended to clear the water from the storage and dispose the collected wastewater properly.

Landscape and Visual

·            The transplanted trees at the new site were in good and healthy condition; and,

·            The berm was habilitated by vegetation.

With the exception of the above observations, the site was in a good orderly manner.  The ET will keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

3.2                                      Implementation Status on Environmental Protection Requirements

The implementation status of environmental mitigation measures and requirements as stated in the EIA Report, Environmental Permits and EM&A Manual during the reporting period is summarized in Annex E.

 

 

4                                            Environmental Monitoring

4.1                                      Air and Noise

Air and Noise monitoring is not required for the project.  

4.2                                      Water Quality

In accordance to the EM&A Manual, water quality monitoring recommenced on 1 September 2008 alongside dredging activities.  QA/QC reports for suspended solids testing are presented in Annex F.  Monitoring data and graphical presentations of the results are included in Annex G. 

Results of the monitoring demonstrated that all measured turbidity, dissolved oxygen (DO) and suspended solids (SS) levels of all Impact Stations were compliant with the Action and Limit (AL) Levels specified in the EM&A Manual. 

4.3                                      POPs Monitoring

Biweekly monitoring of POPs in water samples was conducted on 8 and 22 October for POPs analysis.  At the time of this report, results were available for total PCBs, total DDTs and total PAHs on 8 October.  All POPs parameters were below detection limits.  Monitoring results and QA/QC reports for POPs testing are presented in Annex H.

4.4                                      Waste Management

The Contractor’s revised Waste Management Plan (Revision 4) (WMP) was submitted to the EPD on 20 September 2007.  Pursuant to EP Condition 3.3, the Contractor submitted the updated and revised WMP (Revision 5) to the ET.  The revised WMP has been certified by the ET and IEC, and the revised WMP will be submitted to the EPD in the next reporting month.

4.5                                      Cultural Heritage

The Watching Brief Report, verified by the Independent Environmental Checker, was submitted to the EPD and AMO on 9 May 2008.

4.6                                      Landscape and Visual

According to the EIA report and EM&A Manual, mitigation measures and site inspection are required during the landscaping/planting works.  The berm/landscaping bund was habilitated by vegetation which was grown during the project suspension period.  The transplanted trees were in good and healthy condition.

The weekly site inspections included audits on landscape and visual issues to ensure that the site was in orderly acceptable manner.

4.7                                      Land Contamination, Hazard to Life and Fuel Spill Risk

The ET and IEC verified updated design audit plan was submitted to the EPD on 7 November 2007.

Weekly site inspection covered the waste management aspects which included measures to prevent land contamination by chemical wastes.

4.8                                      Ecology

Dolphin Visual Monitoring

In accordance with EM&A Manual, dolphin monitoring has been undertaken during dredging activities since 1 September 2008.  During the reporting period, a total of 9 dolphin sightings were recorded.  Appropriate action was taken in accordance with the EM&A Manual.  The sighting locations and field records are presented in Annex I.

4.9                                      EM&A Manual

The EM&A Manual for the Project has been updated by the ET to include the detailed arrangements of setting up a Community Liaison Group, carrying out design audit, and monitoring of Persistent Organic Pollutants during construction of the Project.  Further comments were received from the EPD on 22 January 2008.  The ET will update the EM&A Manual which will be submitted to the EPD within the next reporting month.

4.10                                  Baseline Water Quality Monitoring

The Final Baseline Monitoring Report was submitted to the EPD on 20 February 2008 and placed under the EIAO register.

 

 

5                                            Future Key Issues

5.1                                      Key Issues for the Next One Month

It should be noted that dredging activities have been resumed from 1 September 2008.  As such, the key issues to be considered in the next one month will be:

·         Dust release and suppression;

·         Operation of dredging activities; and,

·         Water quality monitoring and dolphin monitoring during the dredging activities

5.2                                      Impact Prediction for the Next One Month

Provided that environmental mitigation measures including good on-site practises are properly implemented, it is not expected that unacceptable adverse impacts will arise.

5.3                                      Works and Monitoring Schedule for the Next One Month

Work programme for the next one month includes jetty platform works (non-piling), site works (construction works for tank farm, operational and fire services buildings, pump platform, drainages, bund wall, security wall etc) and dredging operations.  Weekly site inspections will be undertaken.  Water quality and dolphin monitoring will be undertaken in accordance with the EM&A Manual.