Contents

                        Executive summary                                                             

1                      Introduction                                                                          

1.1                   Purpose of the Report                                                     

2                      Environmental Status                                                      

2.1                   Project Area                                                                         

2.2                   Environmental Sensitive Receivers                            

2.3                   Major Construction Activities                                     

2.4                   Monitoring Schedule of The Reporting Month    

2.5                   Status of Environmental Approval Documents

2.6                   Community Liaison Group Meeting                               

2.7                   Summary of Non-Compliance With The Environmental Quality Performance Limits                                                                                           

2.8                   Summary of Environmental Complaints                  

2.9                   Summary of Environmental Summons                      

3                      Environmental Issues and Actions                             

3.1                   Previous Environmental Deficiencies and Follow-up Actions       

3.2                   Implementation Status on Environmental Protection Requirements

4                      Environmental Monitoring                                             

4.1                   Air and Noise                                                                           

4.2                   Water Quality                                                                        

4.3                   POPs Monitoring                                                                   

4.4                   Waste Management                                                             

4.5                   Cultural Heritage                                                              

4.6                   Landscape and Visual                                                        

4.7                   Land Contamination, Hazard to Life and Fuel Spill Risk 

4.8                   Ecology                                                                                    

4.9                   EM&A Manual                                                                          

4.10                 Baseline Water Quality Monitoring                           

5                      Future Key Issues                                                                 

5.1                   Key Issues for the Next One Month                            

5.2                   Impact Prediction for the Next One Month            

5.3                   Works and Monitoring Schedule for the Next One Month    

 

LIST OF TABLES

Table 2.1        Summary of Works Undertaken During the Reporting Period

Table 2.2        Cumulative Quantity of Excavated Marine Sediments up to 31 January 2009

Table 2.3        Summary of Environmental Licensing, Notification and Permit Status

 

LIST OF ANNEXES

Annex A      Project Location

Annex B      Water Quality and Ecological Sensitive Receivers

Annex C     Cumulative Complaints Statistics

Annex D     Implementation Programme of Mitigation Measures

 


EXECUTIVE SUMMARY

The construction works for the Permanent Aviation Fuel Facility resumed on 9th July 2007.  This twenty-eighth monthly Environmental Monitoring and Audit (EM&A) report presents the EM&A work carried out during the period from 1 February to 28 February 2009 in accordance with the EM&A Manual.

Breaches of all Action and Limit Levels

No water quality monitoring was conducted (due to no dredging work) during the reporting period that required comparison against Action and Limit Levels.

Complaint Log

No environmental complaints were received during the reporting period.

Notifications of any Summons and Successful Prosecutions

No environmental summons or prosecutions were received in this reporting period.

Reporting Changes

There was no reporting changes in the reporting period. 

Future Key Issues

·         Dust release and suppression.

 


1                                            Introduction

Leighton Contractors (Asia) Limited (LCAL) has appointed ERM-Hong Kong, Limited (ERM) as the Environmental Team (ET) to implement the Environmental Monitoring and Audit (EM&A) programme for the Permanent Aviation Fuel Facility (the Project) during construction works. 

The construction works for PAFF commenced in November 2005 based upon the previous EIA (EIAO Register Number AEIAR-062-2002) conducted and the Environmental Permit EP-139/2002 granted on the 28th August 2002.  Due to minor changes to the detailed layout of the site and the site boundary, application for Variation to the Environmental Permit (VEP) (VEP-133/2004) was submitted to the Director of Environmental Protection (DEP) for approval.  The variation to the EP (EP-139/2002/A) was granted by the EPD in February 2004.

The decision by the EPD to grant the above Environmental Permit was, however, subject to a Judicial Review.  The Judicial Review sided in the favour of the DEP, as did the subsequent Judgement from the Court of Appeal from the High Court for Judicial Review in March 2005.  However, the DEP’s decision to grant the EP was quashed by the Judgement of the Court of Final Appeal of July 2006.

The construction works were stopped following the Judgement of the Court of Final Appeal of July 2006.  As such, in order to continue with the construction of the project, the project went through the statutory procedures under the EIAO again with a new design in order to obtain an environmental permit.  The revised EIA was submitted in 2007 and the environmental permit (EP-262/2007) was granted in May 2007.  EP-262/2007 has been amended to EP-262/2007/A and issued by the EPD on 30 November 2007.  A further Variation to the Environmental Permit has been approved to allow dredging works to continue until March 2008.  As such, EP-262/2007/A has been amended to EP-262/2007/B and issued by the EPD on 27 February 2008.

The construction works and EM&A requirements were resumed on 9th July 2007 following the latest requirements of the EP-262/2007/B and EM&A Manual.  Details regarding the EM&A requirements and changes should refer to the updated EM&A Manual.  For the marine works, all piling activities were completed before the previous suspension of construction works in 2006.

1.1                                      Purpose of the Report

This is the twenty-eighth EM&A Report which summarizes the monitoring results and audit findings for the EM&A programme during the reporting period from 1 February to 28 February 2009.

 

2                                            Environmental Status

2.1                                      Project Area

The project area is in Area 38 of Tuen Mun and the pipelines are located in Urmston Road between Tuen Mun Area 38 and Sha Chau.  The site is illustrated in Annex A.

2.2                                      Environmental Sensitive Receivers

No air and noise sensitive receivers were identified close to the project area.  However, water sensitive receivers and ecological sensitive receivers were identified in the EIA study, and are shown in Annex B.

2.3                                      Major Construction Activities

A summary of the major works undertaken in this reporting period is shown in Table 2.1.  Table 2.2 presented the cumulative quantity of excavated materials up to 31 January 2009, the period at which dredging operations ceased.  The cumulative dredging volume during the reporting period was presented in Figure 2.1. 

Table 2.1        Summary of Works Undertaken During the Reporting Period

Area

Works undertaken

Tuen Mun Area 38

Tank Farm, Roof Truss and Bund Wall Construction

Permanent Drainage Construction

Operational & Fire Services Buildings Construction

Jetty Works (Non-piling)

 

Submarine Pipeline Route

None

Table 2.2        Cumulative Quantity of Excavated Marine Sediments up to 31 January 2009

Type of Excavated Materials

Cumulative Bulk Volume (m3)

From 17 December 2007 to 31 March 2008

Contaminated Mud

105,974

Uncontaminated Mud

97,815

 

From 1 September 2008 to 31 January 2009

Contaminated Mud

0

Uncontaminated Mud

149,147

2.4                                      Monitoring Schedule of The Reporting Month

No water quality monitoring was conducted during the reporting period, hence presentation of the monitoring schedule is not applicable. 

2.5                                      Status of Environmental Approval Documents

A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project since July 2007 is presented in Table 2.3. 

Table 2.3        Summary of Environmental Licensing, Notification and Permit Status

Permit/ Licenses/ Notification

Reference

Validity Period

Remarks

Environmental Permit

EP-262/2007/B

Throughout Project

Issued on 27 February 2008 (EP-262/2007/A on 30 November 2007, EP-262/2007 issued on 31 May 2007, EP-139/2002 originally granted on 28 August 2002 and EP-139/2002/A granted on 24 February 2004 were superseded)

 

Chemical Waste Producer Registration

 

WPN 5111-421-L2174-25

Throughout Project

Issued on 10 November 2005

Notification of Construction Works under Air Pollution Control (Construction Dust) Regulation

 

H2104/U1D/5542/DG/DH/PL

 

Throughout Project

Notification on 6 July 2007

Construction Noise Permit

GW-RW0676-07

21 December 2007 to 19 June 2008 (renewal application was in progress)

 

For land-based works including air compressors, breakers, excavators, wheeled loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar benders/cutters, wood saws, grinders, submarine water pump, lorries with crane, dump trucks, rollers, ventilation fans and generators

 

 

GW-RW0677-07

21 December 2007 to 29 February 2008

For marine dredging operation including grab dredger, tug boat, split hopper barge and motor sampan

 

 

GW-RW0678-07

21 December 2007 to 18 June 2008

 

 

For marine jetty works including concrete pump derrick barges, hand-held grinders, generators, air compressors, boring machines, water pumps, tug boat, grout mixers and grout pumps

 

 

GW-RW0094-08

1 March to 31 March 2008

For marine dredging operation including grab dredger, tug boat, split hopper barge and motor sampan

 

 

GW-RW0312-08

04 July 2008 to 22 December 2008

 

 

For marine jetty works including concrete pump derrick barges, hand-held grinders, generators, air compressors, boring machines, water pumps, tug boat, grout mixers and grout pumps

 

 

GW-RW0313-08

04 July 2008 to 19 December 2008

 

For land-based works including air compressors, breakers, excavators, wheeled loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar benders/cutters, wood saws, grinders, submarine water pump, lorries with crane, dump trucks, rollers, ventilation fans and generators

 

 

GW-RW0373-08

1 August 2008 to 20 January 2009

For land-based works including air compressors, breakers, excavators, wheeled loaders, mobile cranes, concrete lorry mixers, hand-held pokers, bar benders/cutters, wood saws, grinders, submarine water pump, lorries with crane, dump trucks, rollers, ventilation fans, generators, stirrer, jet chisel, water jet machine and dehumidifier

 

 

GW-RW0368-08

1 September to 30 November 2008

For marine dredging operation including grab dredger, tug boat, split hopper barge and motor sampan

 

 

GW-RW0054-09

16 February 2009 to 5 August 2009

 

For land-based and marine works including passenger launch, winch, welding machine, grinder, generator, power pack, tug boat, crane, air compressor, roller, hoist and derrick barge

 

Marine Dumping Permit

EP/MD/08-064

13 December 2007 to 29 February 2008

 

For Type 1 – Open Sea Disposal

 

EP/MD/08-065

13 December 2007 to 12 January 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/08-071

13 January 2008 to 12 February 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/08-090

3 March to 31 March 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/08-091

3 March to 31 March 2008

 

For Type 1 – Open Sea Disposal

 

EP/MD/09-018

1 September to 30 September 2008

 

For Type 1d & Type 2 marine disposal

 

EP/MD/09-032

1 October to 31 October 2008

For Type 1d & Type 2 marine disposal

 

 

EP/MD/09-017

1 September to 30 November 2008

 

For Type 1 – Open Sea Disposal

 

EP/MD/09-039

1 December 2008 to 31 January 2009

For Type 1 – Open Sea Disposal

Wastewater Discharge License

EP760/421/011399/l

15 March 2006 to 31 March 2011

Issued on 15 March 2006

2.6                                      Community Liaison Group Meeting

According to the EP requirements, a Community Liaison Group (CLG) shall be established within three months after commencement of construction of the Project.  The major duty of the CLG is to advise on and monitor the proper design, construction and operation of the Project.  The CLG comprises representatives from Airport Authority, members of Tuen Mun community and academics.  The details of the CLG (including Membership and its Terms of Reference) can be found on the Project website (http://www.paffhk.com).

2.7                                      Summary of Non-Compliance With The Environmental Quality Performance Limits

No environmental non-compliance was found during the reporting period. 

2.8                                      Summary of Environmental Complaints

No environmental complaints were received during the reporting period.  A summary of environmental complaints since project commencement is presented in Annex C.

2.9                                      Summary of Environmental Summons

No summons was received in this reporting period.  A summary of legal proceeding since project commencement is presented in Annex C.

 

3                                            Environmental Issues and Actions

3.1                                      Previous Environmental Deficiencies and Follow-up Actions

As no environmental complaint was received over the last reporting period, no follow-up action was required.

Site inspections were carried out by the ET on 3 and 13 February 2009.  Overall, the site was in good orderly manner and no non-compliance was found.  Environmental deficiencies and follow-up actions/mitigation measures were identified during the inspections, as follows:

Air Quality

·            On 3 February 2009, the Contractor was reminded to water regularly on the unpaved areas as well as during sediment excavation to avoid dust generation.

Water Quality

·            On 3 February 2009, stagnant water pools were observed outside site office and site entrance.  The Contractor was reminded to arrange ad hoc water clearance as necessary.

Waste Management

·            On 3 February 2009, empty waste oil containers were found outside operational building without proper receptacle.  The Contractor was reminded to replace bins for temporary storage as soon as possible.

·            On 13 February 2009, general and construction wastes in the tank farm area were observed to be full.  The Contractor was recommended to arrange collection of general wastes by a licensed Contractor as soon as possible.

·            On 13 February 2009, oil sheens were observed on the lids of containers in the chemical storage areas.  The Contractor was recommended to clear spillages and to provide suitable spillage control measures as soon as possible.

With the exception of the above observations, the site was in a good orderly manner.  The ET will keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

3.2                                      Implementation Status on Environmental Protection Requirements

The implementation status of environmental mitigation measures and requirements as stated in the EIA Report, Environmental Permits and EM&A Manual during the reporting period is summarized in Annex D.

 

4                                            Environmental Monitoring

4.1                                      Air and Noise

Air and Noise monitoring is not required for the project.  

4.2                                      Water Quality

No dredging activities were scheduled from 1 February 2009 onwards.  Water quality monitoring was therefore not required for the reporting month.

4.3                                      POPs Monitoring

Persistent organic pollutants (POPs) monitoring was not required since there was no dredging operation during the reporting month. 

4.4                                      Waste Management

According to EP Condition 3.3, the Contractor’s revised Waste Management Plan (Revision 5) (WMP), which has been certified by the ET and IEC, was submitted to the EPD on 05 November 2008. 

4.5                                      Cultural Heritage

The Watching Brief Report, verified by the Independent Environmental Checker, was submitted to the EPD and AMO on 9 May 2008.

4.6                                      Landscape and Visual

According to the EIA report and EM&A Manual, mitigation measures and site inspection are required during the landscaping/planting works.  The berm/landscaping bund was habilitated by vegetation which was grown during the project suspension period.  The transplanted trees were in good and healthy condition.

The weekly site inspections included audits on landscape and visual issues to ensure that the site was in orderly acceptable manner.

4.7                                      Land Contamination, Hazard to Life and Fuel Spill Risk

The ET and IEC verified updated design audit plan was submitted to the EPD on 7 November 2007.

Weekly site inspection covered the waste management aspects which included measures to prevent land contamination by chemical wastes.

4.8                                      Ecology

Dolphin Visual Monitoring

Dolphin visual monitoring was not required as no dredging works were scheduled for the reporting period. 

4.9                                      EM&A Manual

The EM&A Manual for the Project has been updated by the ET to include the detailed arrangements of setting up a CLG, carrying out design audit, and monitoring of Persistent Organic Pollutants during construction of the Project.  A revised EM&A Manual has been verified by the IEC and was submitted to EPD on 2 December 2008.  Further comments were received from the EPD on 16 January 2009 and the ET will revise the Manual in the next reporting month.

4.10                                  Baseline Water Quality Monitoring

The Final Baseline Monitoring Report was submitted to the EPD on 20 February 2008 and placed under the EIAO register.

 

5                                            Future Key Issues

5.1                                      Key Issues for the Next Month

Key issue to be considered in the next month will be:

·         Dust release and suppression.

5.2                                      Impact Prediction for the Next Month

Provided that environmental mitigation measures including good on-site practises are properly implemented, it is not expected that unacceptable adverse impacts will arise.

5.3                                      Works and Monitoring Schedule for the Next Month

Work programme for the next month includes jetty platform works (non-piling) and site works (construction works for tank farm, operational and fire services buildings, drainages, bund wall, security wall etc).  Weekly site inspections will be undertaken.