2.2 Environmental Sensitive
Receivers 2
2.3 Major Construction
Activities 2
2.4 Monitoring Schedule of The
Reporting Month 2
2.5 Status of Environmental
Approval Documents 2
2.6 Summary of non-compliance
with the environmental quality performance limits 3
3 Environmental
Issues and Actions 5
3.1 Previous Environmental
Deficiencies and Follow-up Actions 5
3.2 Implementation Status on
Environmental Protection Requirements 6
3.3 Environmental Monitoring 7
4.1 Key Issues for the Next One
Month 10
4.2 Impact Prediction for the
Next One Month 10
4.3 Works and Monitoring Schedule for the Next One Month 10
LIST OF TABLES
Table 2.1 Summary of Works Undertaken During the Reporting
Period, between 15th January and 14th February 2006
Table 2.2 Summary of Environmental Licensing, Notification and
Permit Status
Table 3.1 Broadband Noise Levels and Noise Attenuation within the Broadband Range 100 Hz to 25.6 kHz
LIST OF ANNEXES
Annex A Water Quality Monitoring Stations, Water Quality and Ecological
Sensitive Receivers
Annex C Implementation Programme of Mitigation Measures
Annex D Action Plan for Dolphin Monitoring
Annex E Cumulative Complaints Statistics
This third monthly Environmental Monitoring and Audit (EM&A) report presents the EM&A works carried out during the period from 15th January 2006 to 14th February 2006 in accordance with the EM&A Manual.
Breaches of all Action and
Limit Levels
No breaches of action or limit levels was occurred during the reporting month as no monitoring, except visual dolphin monitoring was undertaken. No dolphin was found within or close to the site during the piling activities.
Complaint Log
No environmental complaint was received during the reporting period.
Notifications of any Summons and Successful Prosecutions
No environmental summon or prosecutions was received in this reporting period.
Underwater Noise Monitoring
Results
The performance of the bubble jacket mitigation measures complied with the EP conditions.
Future Key Issues
Key issues to be considered in the next one month will include:
· Impacts on dolphins due to piling works;
· Noise from operating machinery and equipment; and,
· Dust release and suppression.
Leighton Contractors (
This is the 3rd EM&A report which summarizes the monitoring results and audit findings for the EM&A programme during the reporting period from 15th January 2006 to 14th February 2006.
The project area is in Area 38 of Tuen Mun
and the pipelines are located in
No air and noise sensitive receivers were identified close to the project area. However, water sensitive receivers and ecological sensitive receivers were identified in the EIA study, and are shown in Annex A.
A summary of the major works undertaken in this reporting period is shown in Table 2.1.
Table 2.1 Summary of Works Undertaken During the Reporting Period, between 15th January and 14th February 2006
Area |
Works undertaken |
Tuen Mun Area 38 |
Marine Piling Works Site Preparation Works Surcharge construction |
Only dolphin visual monitoring was conducted during the piling activities over the reporting month. Piling activities were conducted during the 18th to 27th January, and 6th to 14th February except the 11th February 2006, Sundays and public holidays.
A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project as of 14th February 2006 is presented in Table 2.2.
Table 2.2 Summary of Environmental Licensing, Notification and Permit Status
Permit/ Licenses/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
EP-139/2002 |
Throughout Project |
Issued on 2 August 2002 |
|
|||
Variation of Environmental
Permit |
VEP-133/2004 |
Throughout Project |
Issued on 28 January 2004 |
Amended Environmental
Permit |
EP-139/2002/A |
Throughout Project |
Issued on 24 February 2004 |
Chemical Waste Producer
Registration |
WPN 5111-421-L2174-25 |
Throughout Project |
Issued on 10 November 2005 |
Notification of
Construction Works under Air Pollution Control (Construction Dust) Regulation |
001004989 |
Throughout Project |
Notification on 5 November
2005 (Tank Farm at TM Area 38, Jetty at |
Construction Noise Permit |
PP-RW0024-05 |
12 Nov 05 to 31 Mar 06 |
Issued on 7 November 2005,
for Hydraulic Hammer (single acting) driving steel pile |
Construction Noise Permit |
GW-RW0785-05 |
7
Dec 05 to 31 Mar 06 |
Issued on 7 December 2005,
for General Works (Welding) at Jetty Area |
Wastewater Discharge
License |
-- |
-- |
Applied on 23 January 06 |
No environmental non-compliance was found during the reporting period.
No environmental complaint was received during the reporting period. A statistical summary of environmental complaints since project commencement is presented in Annex E.
No summons was received in this reporting period. A statistical summary of legal proceeding since project commencement is presented in Annex E.
As no environmental complaint was received over the last reporting period, no follow-up action was required.
Weekly site inspections were carried out by the ET on the 20th, 26th, January 2006, 4th and 10th February 2006. The site was in good orderly manner and no non-compliance was found. Environmental deficiencies and follow-up actions/mitigation measures were identified during the inspections, as follows:
Air Quality
·
No noticeable dust emission
was observed during the stockpile loading activity and vehicle movement within
the site ;
·
Earth mounds (surcharge)
were covered to avoid dust emission. However, a C&D stockpile was found not
covered during the 4th Feb 06 site inspection. Although no dust emission was observed, it was
recommended to the Contractor that the C&D stockpiles should be covered to
avoid potential dust emission. The
C&D stockpile was removed during the 10th Feb 06 site inspection;
·
Unpaved road appeared to be
regularly wetted. The site in general
was also regularly wetted with water sprayed to the dust generating activities;
·
Site temporary
entrance/exit was paved and wheel-washing facility was provided at the site
exit to avoid dust deposit in the access road; and,
·
Main access road within the
site (near the entrance/exit) was paved to avoid dust emission.
Noise
·
No noisy activity was found
during the audit;
·
A silenced generator was
used on the piling barge to reduce noise emission. Noise insulation device was provided at the
bottom of the generator to reduce noise emission from the barge;
·
The air compressor had
already got rubber tires to minimize noise emission from the barge; and,
·
Bubble jacket was used during
the marine percussive piling activity.
Water Quality
·
Sedimentation tank was in
the progress of installation during the reporting month. No wastewater was discharged from the
site. The wastewater generated from the
wheel-washing facility was reused. The
Contractor submitted an application for the wastewater discharge license on 23rd
January 2006;
·
Trench was formed next to
the surcharges to contain any potential release of water generated from the
surcharges;
·
Manholes outside the site
were free of sand;
·
Chemical toilets were
provided on site;
·
No sediment plumes were
observed during the marine piling activities;
Waste Management
·
No chemical waste was disposed during the reporting
month; and,
·
Chemical waste drums were found without labels in
the chemical waste storage facility during the 4th Feb 06 site
inspection. The Contractor was reminded
to label all containers in accordance with the code of practice. The drums were labeled during the 10th
Feb 06 site inspection.
Overall, the site was in a good orderly manner. Suitable mitigation measures, such as the use of water truck regularly and tarpaulin covers should continuous be used to ensure dust emission is avoided on site.
The ET will keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.
The implementation status of environmental mitigation measures and requirements as stated in the EIA Report, Environmental Permits and EM&A Manual during the reporting period is summarized in Annex C.
Air and Noise monitoring was not required for the project. The underwater noise monitoring conducted during the initial PAFF piling activity was part of the ecology monitoring. Results are presented in Section 3.3.7 below.
Water quality monitoring at the monitoring stations was not required as no dredging activity was taken place.
Auditing the Contractor’s Waste Management Plan (WMP) is part of the EM&A requirements. The Contractor submitted their Waste Management Plan on the 19th January 2006 and a revised version on the 11 February. The WMP had been reviewed and comments were made on the 7th and 16th February 2006. It is expected the finalised version of WMP will be submitted to the EPD by the end of February 2006.
As no dredging activity was conducted along the pipe trench during the reporting period, marine archaeological monitoring was not required.
According to the EIA report and EM&A manual, mitigation measures and site inspection are required during the landscaping/planting works. No landscaping or planting works were conducted on site during the reporting period.
The weekly site inspections include audits on landscape and visual issues to ensure that the site was in orderly acceptable manner.
According to the EIA report and EM&A manual, mitigation measures and design phase audit are required to minimise the risk of fuel spill and hazards. As there was no construction works related to such issues in the reporting period, audit on the mitigation design and measures was not required. However, weekly site inspection covered the waste management aspects which included measures to prevent land contamination by chemical wastes.
The action plan for dolphin monitoring is shown in Annex D. A 500m dolphin exclusion zone is enforced during all marine piling operations. A qualified person was present during all piling activities and conducted visual monitoring in accordance with the monitoring requirements. Piling activities were conducted during the 18th to 27th January, and 3rd to 14th February except the 11th February 2006. Dolphins were spotted on the 23rd January, 8th and 9th February 2006 at the distance of 1100m, 800m and 830m respectively during the piling works. No dolphins were observed within the 500m exclusion zone during any of the piling works. The dolphin sighting record sheets are attached in Annex F.
Underwater
Noise Monitoring Study
Underwater Noise Monitoring Study was conducted between 23rd and 25th November 2005. Three boats were employed to take measurement of noise levels at a distance of 250m, 500m and 1000m from the piling barge. Both the ambient and the piling (with mitigated measures) noise levels were recorded. All possible precautions were taken to avoid any interference to the results during the measurements. The Summary Report is attached in Annex G.
Tables 3.1 and 3.2 summarized the results being analyzed from the monitoring data.
Table 3.1 Broadband Noise Levels and Noise Attenuation within the Broadband Range 100 Hz to 25.6 kHz
Position |
EP Criteria (dB) |
Ambient Level (dB) |
Mitigated Noise Level (dB) |
Compliant with EP Criteria |
1 (250m) |
162 |
139 |
146 |
Yes |
2 (500m) |
152 |
128 |
127 |
Yes |
3 (1000m) |
145 |
129 |
128 |
Yes |
Table
3.2 Broadband Noise Levels and Noise
Attenuation within the
Position |
EP Criteria (dB) |
Ambient Level (dB) |
Mitigated Noise Level (dB) |
Compliant with EP Criteria |
1 (250m) |
162 |
133 |
138 |
Yes |
2 (500m) |
152 |
122 |
122 |
Yes |
3 (1000m) |
145 |
124 |
124 |
Yes |
Conclusion
· The mitigation measures were effective. The mitigated noise levels generated from the piling activities complied with the EP requirement.
· The piling noise was negligible over ambient at a distance of 500m or more.
· Background noise levels from heavy marine traffic and construction activities contributed to the high ambient noise levels.
Key issues to be considered in the next one month will include:
· Impacts on dolphins due to piling works;
· Noise from operating machinery and equipment; and,
· Dust release and suppression.
Provided that environmental mitigation measures including good on-site practises are properly implemented, it is not expected that unacceptable adverse impact will arise.
Work programme for the next one month includes piling works and site works. Only dolphin visual monitoring is required during piling activities. Weekly site inspections will also be undertaken. The contractor indicated that piling activities will be conducted during all weekdays (Monday to Saturday) between 7am to 7pm except public holidays in the next reporting period between 15th February and 14th March 2006. Thus, dolphin visual monitoring will be conducted during this period.