Contents

                        Executive summary                                                            I

1                      Introduction                                                                       1

1.1                   Purpose of the Report                                                    1

2                      Environmental Status                                                    2

2.1                   Project Area                                                                         2

2.2                   Environmental Sensitive Receivers                          2

2.3                   Major Construction Activities                                  2

2.4                   Monitoring Schedule of The Reporting Month 2

2.5                   Status of Environmental Approval Documents      2

2.6                   Summary of non-compliance with the environmental quality performance limits                                                          4

3                      Environmental Issues and Actions                          5

3.1                   Previous Environmental Deficiencies and Follow-up Actions   5

3.2                   Implementation Status on Environmental Protection Requirements     7

3.3                   Environmental Monitoring                                        7

4                      Future Key Issues                                                                 9

4.1                   Key Issues for the Next One Month                           9

4.2                   Impact Prediction for the Next One Month       9

4.3                   Works and Monitoring Schedule for the Next One Month 9

 

LIST OF TABLES

Table 2.1    Summary of Works Undertaken During the Reporting Period, between 15th June and 14th July 2006

Table 2.2    Summary of Environmental Licensing, Notification and Permit Status

LIST OF ANNEXES

Annex A    Water Quality Monitoring Stations, Water Quality and Ecological Sensitive Receivers

Annex B     Project Location

Annex C    Implementation Programme of Mitigation Measures

Annex D    Cumulative Complaints Statistics

 


EXECUTIVE SUMMARY

This eighth monthly Environmental Monitoring and Audit (EM&A) report presents the EM&A works carried out during the period from 15th June 2006 to 14th July 2006 in accordance with the EM&A Manual.

Breaches of all Action and Limit Levels

No breaches of action or limit levels was occurred during the reporting month as no monitoring was undertaken. 

Complaint Log

No environmental complaint was received during the reporting period.

Notifications of any Summons and Successful Prosecutions

No environmental summon or prosecutions was received in this reporting period.

Reporting changes

There were no reporting changes in the reporting period. 

Future Key Issues

 

·       Noise from operating machinery and equipment;

 

·       Dust release and suppression.

 


1                                            Introduction

Leighton Contractors (Asia) Limited (LCAL) has appointed ERM-Hong Kong, Limited (ERM) as the Environmental Team (ET) to implement the Environmental Monitoring and Audit (EM&A) programme for the Permanent Aviation Fuel Facility (the Project) during construction works. 

1.1                                      Purpose of the Report

This is the 8th EM&A report which summarizes the monitoring results and audit findings for the EM&A programme during the reporting period from 15th June 2006 to 14th July 2006.

 

2                                            Environmental Status

2.1                                      Project Area

The project area is in Area 38 of Tuen Mun and the pipelines are located in Urmston Road between Tuen Mun Area 38 and Sha Chau.  The site is illustrated in Annex B.

2.2                                      Environmental Sensitive Receivers

No air and noise sensitive receivers were identified close to the project area.  However, water sensitive receivers and ecological sensitive receivers were identified in the EIA study, and are shown in Annex A.

2.3                                      Major Construction Activities

A summary of the major works undertaken in this reporting period is shown in Table 2.1. 

Table 2.1         Summary of Works Undertaken During the Reporting Period, between 15th June and 14th July 2006

Area

Works undertaken

Tuen Mun Area 38

Tank Farm, Bund wall Construction

Permanent Drainage Construction

Operational Building Construction

Landscaping Bund and Hydroseeding

Jetty Works (Non-piling)

2.4                                      Monitoring Schedule of The Reporting Month

No monitoring was conducted during the reporting period.  Water monitoring is expected to be commenced towards the end of the 2006 and dolphin monitoring was completed with the completion of piling activities.

2.5                                      Status of Environmental Approval Documents

A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project as of 14th July 2006 is presented in Table 2.2. 


Table 2.2         Summary of Environmental Licensing, Notification and Permit Status

Permit/ Licenses/ Notification

Reference

Validity Period

Remarks

Environmental Permit

EP-139/2002

Throughout Project

Issued on 2 August 2002

 

Variation of Environmental Permit

 

VEP-133/2004

Throughout Project

Issued on 28 January 2004

Amended Environmental Permit

 

EP-139/2002/A

Throughout Project

Issued on 24 February 2004

Chemical Waste Producer Registration

 

WPN 5111-421-L2174-25

Throughout Project

Issued on 10 November 2005

Notification of Construction Works under Air Pollution Control (Construction Dust) Regulation

 

001004989

Throughout Project

Notification on 5 November 2005 (Tank Farm at TM Area 38, Jetty at Urmston Road and Fuel Pipeline

Construction Noise Permit

PP-RW0024-05

12 Nov 05 to

31 Mar 06

(expired)

Issued on 7 November 2005, for Hydraulic Hammer (single acting) driving steel pile

 

Construction Noise Permit

GW-RW0785-05

7 Dec 05 to 31 Mar 06

(expired)

Issued on 7 December 2005, for General Works (Welding) at Jetty Area

 

Construction Noise Permit

GW-RW0032-06

1 Feb 06 to 31 Jul 06 (withdrawn)

Issued on 26 January 2006, , for general works during restricted hours at Tank Farm Area at Tuen Mun Area 38

Construction Noise Permit

 

Construction Noise Permit

 

Construction Noise Permit

 

 

 

Wastewater Discharge License

GW-RW0159-06

 

 

GW-RW0275-06

 

 

GW-RW0297-06

 

 

 

 

EP760/421/011399/l

1 Apr 06 to 30 Sept 06 (withdrawn)

18 May 06 to 17 Nov 06

 

29 May 06 to 28 Nov 06

 

 

 

15 Mar 06 to 31 Mar 11

Issued on 27 March 2006, for General Works (Welding) at Jetty Area

Issued on 12 May 2006, for General Works (Welding) at Jetty Area

Issued on 26 January 2006, for general works during restricted hours at Tank Farm Area at Tuen Mun Area 38

Issued on 15 Mar 2006

2.6                                      Summary of non-compliance with the environmental quality performance limits

Summary of Environmental Non-compliance

No environmental non-compliance was found during the reporting period.

Summary of Environmental Complaints

No environmental complaint was received during the reporting period.  A statistical summary of environmental complaints since project commencement is presented in Annex D.

Summary of Environmental Summons

No summons was received in this reporting period.  A statistical summary of legal proceeding since project commencement is presented in Annex D.

3                                            Environmental Issues and Actions

3.1                                      Previous Environmental Deficiencies and Follow-up Actions

As no environmental complaint was received over the last reporting period, no follow-up action was required.

Weekly site inspections were carried out by the ET on 16th, 23rd, 30th June and 7th, 14th July 2006.  Overall, the site was in good orderly manner and no non-compliance was found.  Environmental deficiencies and follow-up actions/mitigation measures were identified during the inspections, as follows:

Air Quality

·            Dust emission, caused by vehicle movement within the site was observed during 14th July site inspection.  Although water tanker was used, the Contractor should increase the water spraying frequency on a dry and windy day.  No noticeable dust emission was observed during the stockpile loading activity and vehicle movement during other site inspections;

·            Unpaved road appeared to be regularly wetted during the dry days.  The site in general was also regularly wetted with water sprayed to the dust generating activities;

·            Earth mounds and large stockpiles were covered to avoid dust emission;

·            Site entrance/exit was paved and wheel-washing facility was provided at the site exit to avoid dust deposit in the access road;

·            Main access road within the site (between site office and exit) was paved to avoid dust emission.  Other sections of the major access road in the construction area were paved with stones; and,

·            Hydro-seed was applied to the large stockpile and the landscape bunds.  Hydro-seed will be applied to the new section of the large stockpile.

Noise

·            No noisy activity was found during the audit; and,

·            An air compressor at the Workshop was operated without noise label.  The Contractor was reminded to provide noise labels for all air compressors before they can be used.

 

Water Quality

·            Water pondings were found after rainstorm during the site inspections on 16th, 30th June and 7th July 06.  The Contractor should remove the water pondings soon after the rainstorm;

·            Water was found accumulated in the constructed sump pit during the site inspection on 14th July 06.  The Contractor should either remove the water in the pit or to spray the water ponding with mosquito oil regularly;

·            The wastewater generated from the wheel-washing facility was reused.  However, the wastewater from the wheel-washing facility was seen flooded onto the road surface causing water ponding during 16th June site inspection.  The Contractor should clear the flooded water and control the flooding;

·            Manholes outside the site were free of sand;

·            Site toilets were provided on site.  Septic tank was installed to treat the sewerage from the site toilets.  No sewerage effluent discharge out of the site was made; and,

·            For the wastewater generated from the site canteen, a tank/pit was installed to contain all wastewater generated from the canteen.  The wastewater was collected by licensed operator regularly.

Waste Management

·            A bucket filled with brownish muddy water (probably the wastewater removed from the drip tray of the generator) was found in the chemical waste store near the site office during 30th June site inspection.  The bucket had no label and not sealed.  The Contractor should ensure that all chemical waste should be stored properly in the chemical waste containers with proper labeling.  In addition, water was found accumulated in the drip trays of the chemical waste stores on site during 30th June, 7th and 14th July 06 site inspections.  The Contractor was reminded to ensure that the drip trays are free of water/chemical waste.  If the water within the drip tray appeared contaminated, such should be treated as chemical waste for disposal.  As water was found accumulated in the drip trays of the chemical waste stores during several site inspections, the ET recommended the Contractor to use metal doors instead of curtain/screen that are currently using, to prevent rainwater dripping into the stores.  The Contractor replied that they will consider installing metal doors for the chemical waste stores; and,

·            A stand-alone chemical drum (probably diesel oil for the air compressor) without drip tray was found standing in the water ponding next to the air compressor next to the operational building area during 7th July site inspection.  The Contractor should provide drip trays to contain all chemical drums on site, which should also be located away from water ponding area;

Landscape and Visual

·            The transplanted trees at the new site were in good and healthy conditions; and,

·            Grass appeared to grow well at the landscaping bund.

Overall, the site was in a good orderly manner.  Suitable mitigation measures, such as the use of water truck regularly and tarpaulin covers should continuous be used to ensure dust emission is avoided on site. 

The ET will keep track on the EM&A programme to ensure compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

3.2                                      Implementation Status on Environmental Protection Requirements

The implementation status of environmental mitigation measures and requirements as stated in the EIA Report, Environmental Permits and EM&A Manual during the reporting period is summarized in Annex C.

3.3                                      Environmental Monitoring

3.3.1                                Air and Noise

Air and Noise monitoring was not required for the project.   

3.3.2                                Water Quality

Water quality monitoring at the monitoring stations was not required as no dredging activity was taken place.

According to the wastewater discharge license (industrial trade effluent) issued by the EPD on 15th March 06, the Contractor is required to conduct grab sampling/analysis on SS at the discharge point(s) quarterly.  The Contractor indicated that the sampling was conducted in mid July. 

3.3.3                                Waste Management

The Contractor’s revised WMP (Revision 2) was certified by the ET and IEC, and submitted to the EPD on 3rd May 06.

3.3.4                                Cultural Heritage

As no dredging activity was conducted along the pipe trench during the reporting period, marine archaeological monitoring was not required.

3.3.5                                Landscape and Visual

According to the EIA report and EM&A manual, mitigation measures and site inspection are required during the landscaping/planting works.  Hydroseeding of landscape bunds was conducted on site during the reporting period.  The transplanted trees were in good and healthy conditions. 

The final version of landscaping plan was received by the ET on 12th May 06.  The ET and IEC have reviewed the plan and comments were issued.  The revised Final Landscape Plan was submitted to EPD on 5th July 06.

The weekly site inspections included audits on landscape and visual issues to ensure that the site was in orderly acceptable manner.

3.3.6                                Land Contamination, Hazard to Life and Fuel Spill Risk

According to the EIA report and EM&A manual, mitigation measures and design phase audit are required to minimise the risk of fuel spill and hazards.

The Contractor submitted the Environmental Designs for the tank farm and fuel pipelines to the ET on 24th April 06.  The ET and IEC have reviewed the designs and comments were issued to the Contractor.  The revised designs were submitted to EPD on 5th July 06.

Weekly site inspection covered the waste management aspects which included measures to prevent land contamination by chemical wastes.

3.3.7                                Ecology

Dolphin Visual Monitoring

No dolphin monitoring was conducted as there was no piling or dredging activities implemented during the reporting period.

 

4                                            Future Key Issues

4.1                                      Key Issues for the Next One Month

Key issues to be considered in the next one month will include:

 

·       Noise from operating machinery and equipment;

 

·       Dust release and suppression.

4.2                                      Impact Prediction for the Next One Month

Provided that environmental mitigation measures including good on-site practises are properly implemented, it is not expected that unacceptable adverse impact will arise.

4.3                                      Works and Monitoring Schedule for the Next One Month

Work programme for the next one month includes pile internal works (non-piling) and site works.  Weekly site inspections will be undertaken.